How many days notice must a master plumber give to the commissioner when plumbing work is ready for tests?

Prepare for the New York City Master Plumbers Exam. Enhance your skills with interactive flashcards and multiple-choice questions, each providing hints and explanations. Set yourself up for success!

When a master plumber is ready for plumbing work to undergo testing, they are required to give a two-day notice to the commissioner. This requirement is in place to ensure that the necessary inspections can be scheduled and conducted efficiently. The two-day notice allows adequate time for the commissioner’s office to prepare for the inspection, ensuring compliance with safety regulations and standards set by the city. This provision supports effective planning and coordination between plumbing professionals and regulatory bodies, allowing for thorough evaluations of plumbing systems before they are put into operation.